Chapter 3 – Orlando Amway Center
MyOMLab Operations Management
Heizer, Render and Munson
13th Edition
Find expected times and standard deviations for each activity.
Calculator Preview
Your numbers will vary.
Find expected times and standard deviations for each activity.
Your numbers will vary.
Calculate days for the project to be completed.
Watch a 3 min video to solve this problem
Gives you the normal duration, shortened duration, and the added cost. Asks for the crash cost per period.
Your numbers will vary.
Use the CRP, find the activities that would make up the critical path.
They give you a drawn network with six activities and ask for the duration of the project. Duration is the LONGEST path when adding up the times. So it’s the highest path number when adding up each path.