Quiz – Simple project listing five activities
MyOMLab Operations Management
Heizer, Render and Munson
13th Edition
Use the CRP, find the activities that would make up the critical path.
Use the CRP, find the activities that would make up the critical path.
Given the hours that a small metal shop operates, and if productivity increases by a given %, determine the hours that the plant would have to work to produce a certain number of parts.
Your numbers will vary.
According to the textbook, 3 which strategic concepts allow firms to achieve missions?
They give you a drawn network with six activities and ask for the duration of the project. Duration is the LONGEST path when adding up the times. So it’s the highest path number when adding up each path.
Given a table of 5 different periods and their corresponding values as well as three different weights… calculate the three-period weighted moving average forecast for period 6.
Your numbers will vary.
Given a large grid time schedule with the normal time, crash time, normal cost, and the crash cost… find the total time and cost.
Your numbers will vary.
Given a time-series trend equation… find the forecast for the given period.
Your numbers will vary.
They give you two critical path activities along with the time and cost of each. Asks for which activity should be crashed by one day and what the added cost will be.
Your numbers will vary.
Given two different forecasting techniques… determine which one more accurately forecasts the actual demand.
Your numbers will vary.
Given a giant grid of PPM, OTIF, PPV, and Turns… determine the Supplier Performance Rating.
Your numbers will vary.