P3.03 City Commission of Nashville
Hints
Experts Have Solved This Problem
Please login or register to access this content.
The one hint we can offer (at this point) is that if Activity E comes after BOTH Activities C and D, and if C finishes at 110, and D finishes at 120… you MUST start Activity E at the LATER of those two times. So in this example Activity E MUST start at 120 (that later time of the C and D times). That is the most important trick to drawing the Gantt chart with the tool.
Then the other hint is that the line for E must go horizontally across based on the time for E (10, 20 or 30 for example). Look at the X-axis for this the time reference. Hope that helps. Good luck.