Quiz – Simple project listing five activities
MyOMLab Operations Management
Heizer, Render and Munson
13th Edition
Use the CRP, find the activities that would make up the critical path.
Use the CRP, find the activities that would make up the critical path.
They give you a drawn network with six activities and ask for the duration of the project. Duration is the LONGEST path when adding up the times. So it’s the highest path number when adding up each path.